Airport Master Plan Schedule

The City of Longmont is in the initial process of updating its Airport Master Plan. The Federal Aviation Administration (FAA) defines a Master Plan as, "a comprehensive study of the airport and typically describes short-, medium-, and long-term plans for airport development."

An Airport Master Plan assesses what the airport could become in terms of facilities (runways, taxiways, hangars, etc), while being careful not to discount future possibilities. It provides governing boards with options on how the airport can be developed and which facility projects could be eligible for federal funding.

A typical Master Plan takes approximately a year to a year and a half to complete. This can be shorter or longer depending on the airport and its complexity.

The Master Plan will be prepared using guidelines from the FAA. These guidelines ensure that all voices are heard and considered in the process. In addition, the City of Longmont is utilizing its Public Involvement Process to insure public involvement and feedback opportunities throughout this process.

The first step of this process is establishing the scope of work for the Master Plan. The draft scope of work has been written by staff and has been reviewed by the Community Involvement Committee established by the City Council for this process. This draft will also be reviewed by the City's Airport Advisory Board and then forwarded on for final approval by the City Council. Once the scope of work is finalized, a project schedule will be drafted.

 

**Review the Airport Master Plan Final Report **

 

MASTER PLAN SCHEDULE NOTE:

The following schedule for the Airport Master Plan identifies the general process and places where public involvement will be scheduled in each phase of the project. The City of Longmont will strive to keep the schedule as posted. However, the Federal Aviation Administration must review and approve each section of the Master Plan. The current state of continued Federal Aviation Administration funding by the U.S. Congress is in fluctuation. Therefore, all dates after October 18, 2011 are subject to change. Fourth quarter 2011 dates will be posted when confirmed. Please check back frequently to confirm dates and times of future meetings.

Phase I

Current Progress Time Frame Schedule/Tasks
     

 

Completed

Airport Advisory Board

September 16, 2010

 

 

 

Project Initiation

Project Initiation

  • Establish Community Involvement Committee (CIC; 2 meetings)
  • Develop scope of work with input from CIC, Airport Advisory Board, and City Council
  • Discuss roles, responsibilities, and timelines
  • Formalize public involvement

Completed

Airport Advisory Board

October 14, 2010

Meeting Location:

Council Chambers/Civic Ctr

350 Kimbark Street

  • AAB to review final DRAFT Scope of Work with input from CIC, prior to the Scope of Work being sent to City Council

IMPORTANT: There will be a limited number of copies of this material provided at the meeting. If you plan to attend the meeting and wish to have a copy, please print the above documents to bring with you.

October 14, 2010 Meeting Summary:

The Airport Advisory Board reviewed the Airport Master Plan Scope of Work at the October 14, 2010 meeting. Corrections were asked for and the Board passed a motion 6-0 to forward the Scope of Work to City Council once the corrections are made.

Revisions are being made and a DRAFT revised scope is tentatively scheduled for posting on the web October 21, 2010.

Completed

City Council Meeting

October 26,2010

 

Meeting Location:

Council Chambers/Civic Ctr

350 Kimbark Street

  • AAB presentation and recommendations to City Council on scope of work
  • Present draft scope of work to City Council

 

October 26, 2010 Meeting Summary:

The City Council reviewed the Airport Master Plan documentation at the October 26, 2010 meeting. Council approved the Scope of work with a vote of 6-1.

In the meeting, the City Council also approved with a 6-1 vote, to end the involvement of the Community Involvement Committee (CIC) in the remainder of the Master Plan Process. Below is the updated and most current Airport Master Plan Flowchart with the CIC removed from the document.

 

 

No meetings are scheduled for the month of December - Master Plan process to resume in 2011.

Project Information Kick-off

Public Information Kick-Off

  • Establish web page with information on master plan, scope of work, and schedule
  • Inform public of master planning process & schedule
  • Describe how to be involved and where to get information
 

 

 

 

Inventory

  • Airfield / Facility Inventory
  • Financial Inventory

Arrow1

   

Forecasting

  • Aviation Forecasting

Double Arrow

Completed

 

 

 

 

 

 

 

Completed

Airport Advisory Board Meeting

June 9, 2011

 

 

 

August 11, 2011 -MEETING CANCELLED

 

 

City Council Meeting

August 16, 2011

 

Working Paper 1

Jviation Presentation 06/09/11 - Master Plan Chapters 1-3

 

  • The August Airport Advisory Board meeting has been cancelled.

 

 

 

 

 

Facility Requirements

  • Airfield
  • FBO
  • Support facilities, etc.

Double Arrow

3rd Quarter 2011

Completed

 

 

 

September 15, 2011

Working Paper 2

Double Arrow

Completed

 

 

 

 

Completed

Community Open House

September 29, 2011

 

 

 

 

City Council Meeting

October 18, 2011

Public Meeting 1

  • Discuss noise abatement, airport inventory, aviation demand forecast and facility requirements

 

   

Alternative Analysis

Analyze major alternatives for:

  • Operational impacts/benefits
  • Cost
  • Future compatibility
  • Environmental concerns

Double Arrow

4th Quarter 2011

 

 

 

 

 

Airport Advisory Board Meeting

October 27, 2011

Working Paper 3

Double Arrow

4th Quarter 2011

We Are Currently Here:

 

 

 

 

 

 

Airport Advisory Board meeting for November 10, 2011 has been cancelled.

 

Community Open House

November 28, 2011

Senior Center, 910 Longs Peak Ave, 4-8 p.m.

 

City Council Meeting

December 6, 2011

Public Meeting 2

 

  • Discuss facility requirements, economic impact and development alternatives.
  • Press Release - Airport meets with FAA over master plan and runway extension

 

4th Quarter 2011 Airport Advisory Board meeting for December 8, 2011 has been cancelled.

Land Use Planning

  • On airport
  • Off airport
  • Zoning/controls

Arrow1

4th Quarter 2011  

Financial Implementation Plan

  • CIP development
  • Funding strategies
  • Financial plan

Arrow1

1st Quarter 2012

 

 

Airport Layout Plans

  • ALP drawing set

 

1st Quarter 2012

 

 

 

Airport Advisory Board Meeting

February 23, 2012

Working Paper 4

 

1st Quarter 2012

 

Community Open House Monday, February 27, 2012

Civic Center Complex

350 Kimbark Street

5-8 p.m.

Public Meeting 3

  • Present final findings and recommendations
  • Update public information

Arrow1

1st Quarter 2012

 

 

 

 

 

We are here:

Arrow

City Council

March 13, 2012 -

Presentation of Chapters

6 - Environmental Overview Analysis, 7 - Financial Implementation Plan, and 8 - Airport Economic Impacts

 

 

March 27, 2012 - Resolution adopting Master Plan

Final Report

 

 

 

 

 

 

  • Review and adoption by City
  • FAA approval
     

 

 

 

 

 

 

-->